Reliability, Replacement & Spares

Three maintenance questions, one lifetime distribution: how reliable is the system, when should we replace a part, and how many spares must sit on the shelf? Turn the Weibull shape β and watch preventive maintenance go from essential to completely pointless - because you cannot prevent random failure.

How to use it

Reliability, replacement, spares

The component

Replacement economics

System & spares

–
Cost rate $/1k hr
–
System reliability @ η/2
–
Spares to stock
Swipe the diagram sideways to see every stage.

Reliability block diagram. Every unit in the chain must work; each stack is parallel redundancy. One weak stage sets the system - reliability multiplies, so series is unforgiving.

Age-replacement cost rate vs replacement age. The dot is the optimum; dashed = run-to-failure. Crosses are simulation checks.

Poisson demand over the lead time. Bars past the red line are the stock-outs your fill rate tolerates.

Try these experiments

  1. Set β = 1.0: the failure rate goes flat (memoryless), and the cost curve loses its minimum - preventive replacement becomes pointless. You cannot prevent random.
  2. Raise β to 4.5: sharp wear-out, and the optimal age tightens well below η. Prevention only makes sense when failures are ageing, not random.
  3. Go from 4 units in series at redundancy 1 to redundancy 2: system reliability leaps. Adding a spare in parallel beats making each unit slightly better.

About this tool

The concept

Three linked maintenance questions: how reliable is the system, when should we replace, and how many spares do we hold? All three fall out of one lifetime distribution.

How it works

Weibull R(t)=e−(t/η)β. Age replacement cost rate = [cpR(T) + cf(1−R(T))] / ∫0TR(t)dt. Spares: smallest s with Poisson CDF(s; λL) ≥ fill rate.

Winning strategy

Check β before you buy a preventive-maintenance programme. β≤1 means failures are random or infant-mortality - scheduled replacement then adds cost and achieves nothing.

Background: Weibull distribution · Reliability engineering · Barlow & Proschan (1965)